2022-12-11Balticconnector Offshore Gas Pipeline Insurance (Baltic Connector Oy)
Renewal of operational insurances of Balticconnector Offshore gas pipeline between Finland and Estonia for year 2023
- Property
- Third Party Liability
The gas pipe is owned 50/50 Baltic Connector Oy (Finland) and Elering AS (Estonia)
Näytä hankinnat »
2020-11-19Baltic Connector Offshore Gas Pipeline Insurance (Baltic Connector Oy)
Renewal of operational insurances of balticconnector offshore gas pipeline between Finland and Estonia for year 2021:
— property and business interruption,
— third party liability.
The gas pipe is owned 50/50 Baltic Connector Oy (Finland) and Elering AS (Estonia).
Näytä hankinnat »
2017-11-14Resourcing and Recruitment Services for Balticconnector Offshore Project (Baltic Connector Oy)
Contracting Authorities invite economic operators to participate in the procurement for offshore and other project related resourcing, staffing and recruitment services. It is the intention of the Contracting Authorities to establish a framework agreement together with 3-4 economic operators (service providers) which will be responsible for searching, recruiting, hiring/contracting and mobilizing experienced project management, project administration and engineering professionals for the Balticconnector …
Näytä hankinnat »
2017-11-08Balticconnector Onshore Pipeline Siuntio — Inkoo, Civil and Installation Works (Baltic Connector Oy)
The scope of the contract comprises of the civil and installation works in accordance with the procurement documents.
Gas pipeline materials (line pipes, valves, fittings, pig traps, insulation joints) will be provided by the Contracting Authority. Other materials will be provided by the contractor. Pipeline detail design will be provided by the Contracting Authority.
Civil and installation contractor will be assigned as the main contractor responsible for work planning and management on site, site …
Näytä hankinnat »
2017-06-02Balticconnector: Manufacturing and Supply of Offshore Line Pipe (Baltic Connector Oy)
Baltic Connector Oy and Elering As are planning to construct the Balticconnector Pipeline, a bi-directional natural gas pipeline to connect Finland and Estonia.
This procurement procedure covers the supply of line pipe completed with internal flow coating, external corrosion coating, concrete weigh coating including supply and installation of aluminum anodes on part of the line pipes.
This is a joint procurement of Baltic Connector Oy and Elering AS. Baltic Connector Oy is the Contracting Authority …
Näytä hankinnat »
2017-05-11Balticconnector NG pipeline 20"/ DN500 Line Pipes (Baltic Connector Oy)
The scope of the contract covers the supply of line pipes completed with internal flow coating and external corrosion coating.
The supplies and services will be described in more detail in the specifications which will be provided to the Candidates invited to the negotiations.
Näytä hankinnat »
2017-04-28Balticconnector: Manufacturing and Supply of Offshore Line Pipe (Baltic Connector Oy)
Baltic Connector Oy and Elering As are planning to construct the Balticconnector Pipeline, a bi-directional natural gas pipeline to connect Finland and Estonia.
This procurement procedure covers the supply of line pipe completed with internal flow coating, external corrosion coating, concrete weigh coating including supply and installation of aluminum anodes on part of the line pipes.
This is a joint procurement of Baltic Connector Oy and Elering AS. Baltic Connector Oy is the Contracting Authority …
Näytä hankinnat »
2017-04-28Balticconnector: Seabed and Pipelay Installation (Baltic Connector Oy)
Baltic Connector Oy and Elering As are planning to construct the Balticconnector pipeline, a bi-directional natural gas pipeline to connect Finland and Estonia.
The scope of the contract includes management, engineering, construction of seabed intervention and offshore pipeline construction works and pre-commissioning:
This is a joint procurement of Baltic Connector Oy and Elering AS. Baltic Connector Oy is the contracting authority responsible for carrying out the procurement procedure. Baltic Connector …
Näytä hankinnat »
2016-10-03Engineering, procurement and construction management services (‘EPCM Services’) — Balticconnector high pressure... (Baltic Connector Oy)
The Balticconnector project is a gas infrastructure project aiming to interconnect the Finnish and Estonian gas networks in co-operation of Baltic Connector Oy and Elering AS. Project planning support from the EU within the framework of the CEF program was agreed in May 2015.
The contract to be awarded on the basis of the current procurement procedure shall cover the EPCM services required for the implementation of the high pressure compressor and ultrasonic custody metering station in Finland. The scope …
Näytä hankinnat »
2016-10-03Engineering, procurement and construction management services (‘EPCM Services’) — Balticconnector High Pressure... (Baltic Connector Oy)
The Balticconnector project is a gas infrastructure project aiming to interconnect the Finnish and Estonian gas networks in co-operation of Baltic Connector Oy and Elering AS.
The contract to be awarded on the basis of the current procurement procedure shall cover the EPCM services required for the implementation of 22 km high pressure onshore pipeline in Finland. Together with detail engineering the scope of the contract shall also cover permitting services, project and construction management as well …
Näytä hankinnat »
2016-09-13Baltic Connector Oy: Projektinhallintapalvelu ja tekninen suunnittelupalvelu (Owner's Engineering -palvelut) (Baltic Connector Oy)
Baltic Connector Oy on valtionyhtiö, joka perustettiin vuonna 2015 toteuttamaan Suomen osuutta Balticconnector -kaasuputkihankkeesta.
Balticconnector on Suomen ja Viron yhdistävä kaasuputkihanke, joka mahdollistaa Baltian maiden ja Suomen kaasumarkkinoiden yhdistämisen ja integroitumisen EU:n yhteisiin energiamarkkinoihin. Lisäksi muun Baltian kaasuinfrastruktuurin rakentaminen mahdollistaa kaksisuuntaisen kaasuliikenteen Viron ja Latvian välillä, joka yhdessä Balticconnectorin kanssa antaa Suomelle ja …
Näytä hankinnat »
2016-07-29Balticconnector Geophysical and Geo-technical Seabed Surveys (Baltic Connector Oy)
The current procurement procedure shall cover the geo-physical and geo-technical studies for the design and construction of the Balticconnector offshore pipeline. The objective of the survey is to provide detailed information about the seabed including hardness of outcropping bedrock, type of soil, grain size distribution, relative density, undrained shear strength etc. The awarded tenderer shall be responsible for the execution of the surveys.
Näytä hankinnat »
2016-07-25Baltic Connector Oy: oikeudelliset palvelut (Baltic Connector Oy)
Baltic Connector Oy on valtionyhtiö, joka perustettiin vuonna 2015 toteuttamaan Suomen osuutta Balticconnector-kaasuputkihankkeesta.
Balticconnector on Suomen ja Viron yhdistävä kaasuputkihanke, joka mahdollistaa Baltian maiden ja Suomen kaasumarkkinoiden yhdistämisen ja integroitumisen EU:n yhteisiin energiamarkkinoihin. Lisäksi muun Baltian kaasuinfrastruktuurin rakentaminen mahdollistaa kaksisuuntaisen kaasuliikenteen Viron ja Latvian välillä, joka yhdessä Balticconnectorin kanssa antaa Suomelle ja …
Näytä hankinnat »
2016-07-15Engineering, Procurement and Construction Management Services (‘EPCM Services’) — Balticconnector High Pressure... (Baltic Connector Oy)
The Balticconnector project is a gas infrastructure project aiming to interconnect the Finnish and Estonian gas networks in cooperation of Baltic Connector Oy and Elering AS. Project planning support from the EU within the framework of the CEF program was agreed in May 2015. The contract to be awarded on the basis of the current procurement procedure shall cover the EPCM services required for the implementation of the high pressure offshore pipeline. The scope of the contract shall also cover geophysical …
Näytä hankinnat »