Hankinnat: Kattilalaitteistot

>20 arkistoidut hankinnat

Viimeaikaiset hankinnat kattilalaitteistot osoitteessa Suomi

2023-06-06   Pre-qualification for turnkey delivery of electric boiler to Nuijala heat station (Fortum Power and Heat Oy)
Fortum is planned to invest in Nuijala, Espoo with a new approx. 50-60 MW electric boiler, a 20,000 m3 district heat accumulator and DH pumping systems (the “Plant”). The Plant will store, produce, and deliver heat to Fortum district heating network in Espoo and Kirkkonummi. The Plant is designed to be operated remotely from the main control room at Suomenoja power plant (approx. 10 km from the Nuijala Plant). However, there will be a small local control room at the Plant for commissioning, start-up, … Näytä hankinnat »
2023-02-15   Karjaan uusi biolämpökeskus BIO5 (Raseborgs Energi Ab / Raaseporin Energia Oy)
Raseborgs Energi Ab / Raaseporin Energia Oy on hankkimassa uutta biolämpökeskusta Karjaalle. Uusi lämpökeskus rakennetaan samalle, osoitteessa Timpurintie 9, Karjaa, sijaitsevalle tontille nykyisen biolämpökeskuksen kanssa. Olemassa oleva lämpökeskus jää käyttöön. Uuden lämpökeskuksen toimituslaajuuteen kuuluvat kaikki lämmöntuotantoon tarvittavat laitteet, kuten kiinteän polttoaineen kattila (myöhemmin KPA-kattila), pumput, lämmönvaihtimet, savukaasun puhdistuslaitteet sekä sähköistys ja automaatio. … Näytä hankinnat »
Mainitut toimittajat: Jernforsen Energy AB
2023-01-30   RENEWAL OF ECONOMIZER TO KIVENLAHTI BIO-HEATING PLANT, ESPOO FINLAND (Fortum Power and Heat Oy)
Turnkey delivery of economizer to Kivenlahti bio-heating plant. Kivenlahti K4-boiler was commissioned in 2020. The fuel power of the boiler is 49 MW. The fuel is solid wood fuels which consist of recycled wood, forest biomass (forest residues, hard wood chips) and industrial by-products (bark, saw dust). The boiler produces heat to the district heating network of Espoo. The boiler is connected to the district heating network with a heat exchanger. The boiler is a water boiler equipped with a stream drum. … Näytä hankinnat »
2022-10-26   Helen Ltd's procurement of industrial electrode hot water boilers (Helen Ltd)
Helen Ltd (later "Contracting Authority) aims to be carbon neutral energy company by 2030. In order to achieve its carbon neutrality targets, Helen has commited to stop using of coal by 2024, and is currently seeking and piloting non-combustion based energy solutions for its energy production. In this procurement, The Contracting Authority is seeking 1-3 suppliers for insdustrial electrode hot water boilers, preliminary to one to three different production locations in Helsinki area, Finland, as … Näytä hankinnat »
Mainitut toimittajat: Höyrytys Oy PARAT HALVORSEN AS
2022-09-23   Helen Oy:n Salmisaaren voimalaitoksen K7-pölypolttokattilan polttoainekonversio sisältäen kattilan... (Helen Oy)
Helen Oy (jäljempänä Hankintayksikkö tai Tilaaja) suunnittelee toteuttavansa Helsingin Salmisaaren voimalaitoksen kivihiilikäyttöiselle K7-pölypolttokattilalle (SaK7) polttoainekonversion, jossa kattila muutetaan puuperäisen pelletin polttoon perustuvaksi kuplapetikattilaksi (BFB). Hankinnan kohteena on kattilamuutoksen kokonaistoimitus, joka käsittää nykyisen hiilipölykattilan muuttamisen puupellettiä polttavaksi BFB-leijupetikattilaksi, savukaasun puhdistusjärjestelmän uusimisen sekä kattilalaitoksen … Näytä hankinnat »
2022-05-16   VSSHP Ky Tyks T2-sairaala puhdashöyrykehittimet (Varsinais-Suomen sairaanhoitopiirin kuntayhtymä)
Hankinnan kohteena on Varsinais-Suomen sairaanhoitopiirin Tyks T2-sairaalan kaksi puhdashöyrykehitintä tarjouspyynnön liitteenä olevien asiakirjojen mukaisesti. Hankittavien laitteiden tulee soveltua sairaalaan ja niiden tulee täyttää kaikki tarjouspyyntöasiakirjoissa esitetyt vaatimukset ja standardit Tilaaja teettää palokatkotyöt ja LVIAS- ja rakennustekniset työt erillisenä urakkana. Laitteet ovat tilaajan hankinta, joka alistetaan pääurakkaan. Laitetoimittajalle kuuluu kaikki asennukseen liittyvät … Näytä hankinnat »
2022-02-14   Datacenter Heat Pump Plants Espoo and Kirkkonummi: Electrical boilers (Fortum Power and Heat Oy)
Delivery of two electrical boiler plants for the heat pump plants in Finland: one located in Espoo and the other in Kirkkonummi. Näytä hankinnat »
2021-11-15   Kuhmon Lämpö Oy:n 15MW:n kattilalaitos (Kuhmon Lämpö Oy)
15 MW:n KPA- kattilalaitoshankinta täydentämään kaukolämmön ja teollisuuden lämmöntuotantoa. Näytä hankinnat »
2021-11-12   Prequalification of turnkey delivery for electric boiler to Suomenoja power plant (Fortum Power and Heat Oy)
With this request, Fortum Power and Heat Oy wishes to obtain a turnkey delivery for an agreement for the supply of a appox. 50MW new electrode boiler with an associated expansion system, boiler circuit pump, control valves and heat exchanger for Suomenoja heat production facility. The scope will include complete design, engineering, manufacturing, installation, commissioning and training of the Purchaser’s operating and maintenance personnel. General plant and process design and engineering as well as … Näytä hankinnat »
2021-05-19   Joensuun CHP-kattilan biokonversio (Savon Voima Joensuu Oy)
Hankinta sisältää Joensuun CHP-kattilan biokonversion toteuttamisen materiaaleineen ja töineen. Hankinnan sisältö on kuvattu tarkemmin hankintaohjelmassa ja muissa projektipankissa olevissa tarjouspyyntöasiakirjoissa. Hankinnassa noudatetaan yleisiä sopimusehtoja NLM10, hankintaohjelmassa esitetyin poikkeuksin. Tarjouspyyntöasiakirjat löytyvät seuraavan linkin takaa: https://savonvoima-my.sharepoint.com/:f:/g/personal/aki_korkalainen_savonvoima_fi/EpzDd_LjOENGgHi9nk6UStoBoodwOtfqE97ZUyEgYXwI9Q?e=KRTcf1 Näytä hankinnat »
Mainitut toimittajat: Sumitomo SHI FW Energia Oy
2021-05-19   Höyryntuotantokontin vuokraus (Puolustusvoimien Logistiikkalaitos)
Hankinnan kohteena on Puolustusvoimien vaatetuskorjaamon Mikkelin tuotantolaitoksen (osoite Patteristonkatu 1, rakennus U, Mikkeli) prosessienergian muutokseen (raskas polttoöljy korvataan nestekaasulla) liittyvä höyryntuotantokontin vuokraaminen, mikä korvaa vanhan lämpökeskuksen LK95. Hankintasopimus solmitaan neljäksi (4) vuodeksi. Hankintaan sisältyy optiot kahdelle (2) vuodelle. Näytä hankinnat »
Mainitut toimittajat: Steamrator Oy
2020-07-22   Helen Oy:n Suomenlinnan lämpökeskuksen hankinta (Helen Oy)
Hankinnan kohteena on Suomenlinnaan rakennettava uusi lämpökeskus öljysäiliöineen (40 m) suunniteltuna, asennettuna ja käyttöönotettuna (sisältäen kone-, sähkö- ja automaatiokokonaisuudet). Uuden lämpökeskuksen vesiteho on 4,5 MW. Nykyinen Suomenlinnan lämpökeskus (SL06) on kevyellä polttoöljyllä toimiva siirrettävä varalämpölaitos. Hankintaan ei sisälly lämpökeskukselle tarvittavien tilojen rakentamista. Uuden lämpökeskuksen toimittajan tulee varautua siihen, että toimitusaikatauluun voi tulla … Näytä hankinnat »
2020-04-20   50 MW:n KPA-kattilalaitos (Seinäjoen Energia Oy)
Hankinnan kohteena on 50 MW:n KPA-kattilalaitos Kapernaumissa sijaitsevalle lämpölaitokselle. Uusi kattila tulee toimimaan Seinäjoen kaukolämmön peruskuormakattilana. Hankinta sisältää kattilalaitoksen ja lämmön talteenoton rakennuksineen. Hankintaan liittyvät optiot ilmenevät hankintaohjelman kohdasta 4.1.3. Hankintaan sisältyy lisäksi tilaajan optiona vastaavantyyppinen 50 MW:n KPA-kattilalaitos Seinäjoen voimalaitoksen tontille osoitteeseen Sevontie 1. Laitosoption tarkempi määrittely ilmenee … Näytä hankinnat »
Mainitut toimittajat: Valmet Technologies Oy
2020-01-14   Oulun Keskuspesula Oy, höyrykeskus (Oulun Keskuspesula Oy)
Oulun Keskuspesula Oy:n uusien rakennettavien toimitilojen yhteyteen hankittava höyrykeskus, jonka pääpolttoaineena biokaasu. Näytä hankinnat »
Mainitut toimittajat: Adven Oy Höyrytys Oy
2019-09-04   Tampereen Sähkölaitos Oy:n NSL3-projektin kattilalaitos (Tampereen Sähkölaitos Oy)
Tampereen Sähkölaitos Oy rakennuttaa Tampereelle Naistenlahden voimalaitosalueelle polttoaineteholtaan n. 210 MW kiertoleijukerroskattilalaitoksen (CFB) apujärjestelmineen korvaamaan nykyisen Naistenlahti 2 kattilalaitoksen. Pääpolttoaineena uudessa kattilalaitoksessa on biopolttoaineet ja turve. Tässä hankinnassa on kyse kiertoleijukerroskattilalaitoksen hankinnasta sisältäen kattila-apulaitteet sekä kattilalaitosrakennuksen. Hankinta sisältää toimituslaajuuden suunnittelun, materiaalin ja komponenttien … Näytä hankinnat »
Mainitut toimittajat: Valmet Technologies Oy
2019-04-01   Procurement of Boiler Plant and Flue Gas Condensing Plant for Helen Ltd's Vuosaari C (VuC) Bio Heat Plant (Helen Ltd)
Helen Ltd is constructing a Bio Heat Plant with a fuel heat input of 220 MW. The main fuel will be wood based biomass. The procurement consists of a biomass boiler plant based on Circulating Fluidized Bed (CFB) technology, flue gas condensing plant, auxiliary equipment and boiler house. The procurement consists of 2 parts, which may be quoted as following: — Alternative A (parts quoted separately): 1) Boiler Plant; 2) Flue Gas Condensing Plant. — Alternative B (parts quoted together): boiler plant and … Näytä hankinnat »
Mainitut toimittajat: Sumitomo SHI FW Energia Oy Valmet Technologies Oy
2019-03-26   Vantaa WtE2 Lot 1: Grate/Boiler (Vantaan Energia Oy)
Vantaan Energia Oy is planning to construct a new heat only Waste to Energy plant, Wte2, next to the existing WtE plant. The new plant will be constructed mainly as a green field, with some exceptions like DCS and main district heat systems. This notice concerns procurement of Lot 1: Grate/Boiler Plant. The scope of the procurement is specified in appendices. Notice that all times presented are Eastern European summer time (Helsinki, Finland; UTC/GMT +3 hours). Näytä hankinnat »
2019-02-08   Lahti Energia Oy:n Kymijärven voimalaitosten painelaitteiden huolto- ja korjaustöitä sekä asennuspalveluita koskeva... (Lahti Energia Oy)
Hankinnan kohteena on Lahti Energia Oy:n Kymijärven voimalaitosten painelaitteiden huolto- ja korjaustöitä sekä asennuspalveluita koskeva puitejärjestely tarjouspyynnön liitteenä olevan palvelukuvauksen mukaisesti. Näytä hankinnat »
Mainitut toimittajat: SSG Sahala Oy
2019-02-04   Fuel Handling System for Solid Fuel Boiler (Haapajärven Lämpö Oy)
The subject matter of the procurement consists of a fuel handling system including secondary equipment such as chain reclaimers, magnet, screen, crusher and chain conveyors for a 20 MW solid fuel. Näytä hankinnat »
Mainitut toimittajat: Laitex Oy
2018-12-11   Solid Fuel Boiler (Haapajärven Lämpö Oy)
The subject matter of the procurement consists of a 20 MW solid fuel boiler for the heating plant in question, electrostatic precipitator and a flue gas stack as well as a 20 MW auxiliary oil-fired boiler and/or load burner solution. A flue gas scrubber is not included in this delivery. Näytä hankinnat »
Mainitut toimittajat: KPA Unicon Oy
2018-10-30   50 MW:n KPA-kattilalaitos (Seinäjoen Energia Oy)
Seinäjoen Energia Oy on hankkimassa uutta lämpökattilaa Seinäjoen Kapernaumissa sijaitsevalle lämpölaitokselle. Uusi kattila tulee toimimaan Seinäjoen kaukolämmön peruskuormakattilana. Hankinta sisältää kattilalaitoksen ja lämmön talteenoton rakennuksineen. Näytä hankinnat »
2018-10-29   Toppila 2 luvojen perusparannus (Oulun Energia Oy)
Toimituslaajuus on olemassa olevien savukaasuluvojen lämpöpintojen osittainen uusinta sekä palamisilman esilämmityksen tehostaminen kokonaisuudessaan sisältäen suunnittelun, materiaalin ja komponenttien hankinnan, asennuksen, käyttöönoton ja dokumentoinnin. Tarkempi hankinnan kuvaus on esitetty tarjouspyyntödokumenteissa. Näytä hankinnat »
2018-09-05   Flue gas condensing and condensate purification plant (Keravan Lämpövoima Oy)
Keravan Lämpövoima Oy is planning to build a new flue gas condensing and condensate purification plant (FGC plant). The FGC plant is intended to be built to the existing CHP plant (Myllykorventie 20, Kerava, Finland) which is firing mainly woody biomass and milled peat. The fuel input of the power plant is about 80MW. The heat from flue gas condensation will be utilized in heating the district heating water. The flue gas condensate is purified and utilized as plant make-up water (potable water … Näytä hankinnat »
2018-07-04   Framework Agreement for Advanced Boiler Service (Fortum Oyj)
Fortum Oyj, with its affiliated companies, including Stockholm Exergi, has the intention of procuring Framework Agreements for advanced boiler service for the maintenance of its fleet of CHP boilers (Combined heat and power) and HOBs (Heat-only Boilers) in Nordic countries, Baltics and Poland. The procurement will be divided into lots based on different types of services needed for the maintenance of the CHP and HOB plants. Tenderers will have the possibility of offering one or several lots. Tenderers … Näytä hankinnat »
2018-05-11   Höyrynkehitinlaitteiston hankinta (Saimaan Tukipalvelut Oy)
Höyrynkehitinlaitteiston hankinta. Näytä hankinnat »
Mainitut toimittajat: Steamrator Oy
2018-05-09   WtE grate boiler and turbine (Lounavoima Oy)
Lounavoima Oy is planning to construct a new Waste to Energy (WtE) CHP Plant to Korvenmäki, Salo. The new CHP plant will be located at the green field site adjacent to the existing municipal landfill site. Korvenmäki WtE plant is going to use source separated municipal solid waste (MSW) as main fuel. The new plant will be designed for 120 000 t /a waste fuel. The combustion and heat recovery technology is based on grate boiler technology. The WtE plant will be purchased preliminary in 6 packages (Lots). … Näytä hankinnat »
Mainitut toimittajat: Steinmüller Babcock Environment GmbH
2017-12-19   Boiler Wall Openings (Fortum Power and Heat Oy)
Boiler wall opening frames and their installation work to enable 4 new burners and 4 OFA units assembly to a boiler. Näytä hankinnat »
2017-12-19   Biofuel Boiler and Flue Gas Condensing Plant (Fortum Power and Heat Oy)
Delivery of 49 MW (fuel power) solid biofuel fired bubbling fluidised bed hot water boiler plant including flue gas condensing unit. Näytä hankinnat »
2017-12-13   Kotkan Energia Oy, Hovinsaaren Voimalaitos, Vedenkäsittelyn uusinta (Kotkan Energia Oy)
Kotkan Energia Oy:n Hovinsaarenvoimalaitoksen vedenkäsittelyä uudistetaan rakentamalla kokonaan uudet järjestelmät lisäveden valmistukseen, prosessi- ja savukaasulauhteen käsittelyyn. Näytä hankinnat »
2017-05-03   Oulun Energia Oy, Höyrykattilan hankinta (Oulun Energia Oy)
Oulun Energia Oy on käynnistänyt uuden sähköä, kaukolämpöä ja teollisuuden prosessihöyryä tuottavan voimalaitoksen esisuunnittelun. Investointi käsittää uuden polttoaineteholtaan noin 215 MW:n voimalaitoksen, joka sijoitetaan Laanilan Kemiran teollisuusalueella sijaitsevalle tontille. Hankinnan alustava aikataulu on seuraava: — Tarjouspyyntö kesäkuussa. — Tarjoukset ja neuvottelut syyskuussa. — Investoinitpäätös vuoden 2018 alussa. Alustava projektin aloitusaika on helmikuu 2018 ja voimalaitoksen … Näytä hankinnat »
Mainitut toimittajat: Valmet Technologies Oy
2017-04-19   Etelä-Savon Energia Oy – Pursiala 2 economaiser (Etelä-Savon Energia Oy)
Pursiala 2 voimalaitoksen economaiserin valmistus, vanhan economaiserin purku ja uuden asentaminen. Näytä hankinnat »
Mainitut toimittajat: SVS Supervise Service Oy
2017-03-02   Pori Energia Oy, Kattilan hankinta (Pori Energia Oy)
Pori Energia Oy on käynnistänyt Aittaluodon teollisuusalueella sijaitsevan voimalaitoksen modernisoinnin esisuunnittelun. Modernisointiprojekti käsittää uuden kattilalaitoksen toteutuksen. Kattilalaitos on polttoaineteholtaan vähintään 70 MW mutta enintään 99 MW. Kattilalaitosta varten rakennetaan sen tarvitsemat polttoaineen kuljetinjärjestelmät. Kattilalaitos varustetaan savukaasunlauhdutuksella. Alustava projektin aloitusaika on tammikuu 2018 ja voimalaitoksen vastaanotto on maaliskuussa 2020. Näytä hankinnat »
Mainitut toimittajat: Andritz Oy
2016-09-29   Helen Oy:n Salmisaaren B-voimalaitoksen kattilan 1 tulistimien (2 kpl) uusinta (Helen Oy)
Helen Oy:n Salmisaaren B voimalaitoksen (sähköteho 170MW, KL 300MW) AHLSTRÖM-hiilipölykattila (463 MW) tulistimet 1 ja 3 uusitaan kesän 2018 huollossa. Näytä hankinnat »
Mainitut toimittajat: Amec Foster Wheeler Energia Oy
2016-09-22   Artukaisten KPA-Höyrykeskus (Oy Turku Energia – Åbo Energi Ab)
Hankinta koskee noin 12–15 MW:n KPA-höyrykeskuksen ja noin 10 MW:n öljy/nestekaasuhöyrykeskuksen osa- tai kokonaistoimitusta. Kattilat tuottavat noin 10 bar:n höyryä teollisuuskäyttöön ja kaukolämpöä. Hankinnat sisältävät polttoaineen vastaanotto-, siirto ja käsittelyjärjestelmät, höyrykattilat, savukaasujen puhdistuksen, tuhkan poistojärjestelmät, apulaitteet, sähköistyksen, automaation, rakennustekniset työt, asennukset ja käyttöönoton. Tilaaja varaa oikeuden hankkia osajärjestelmiä myös … Näytä hankinnat »
2016-07-08   Helen Oy:n Salmisaaren B-voimalaitoksen apuhöyrykattilan hankinta (Helen Oy)
Hankinnan kohteena on Salmisaaren (Sa) K5 apukattilan uusinta. Kattilalaitos hankitaan kokonaistoimituksena sisältäen kaikki tarveaineet, laitteet ja työsuoritukset, jotka kuuluvat hankintasopimuksen edellyttämään koekäytettyyn ja käyttöönotettuun kattilalaitokseen ja ovat välttämättömiä järjestelmän toiminnalle. Kokonaistoimitus kattaa asennuksen, koeajot ja käyttöönoton, sisältäen suunnittelun, käyttöhenkilökunnan koulutuksen, projektoinnin sekä dokumentaation. Näytä hankinnat »
Mainitut toimittajat: Hansa Power Oy
2016-04-15   KYVO3, Flue Gas Condensing Plant (Lahti Energia Oy)
Lahti Energia Oy will construct a combined heat and power (CHP) plant on the site of Kymijärvi located at the city of Lahti with the fuel firing input capacity of 170 MW using wooden biomass and peat and coal as spare fuel. This procurement concerns a Flue Gas Condensing (FGC) Plant including scrubber and/or flue gas condenser, combustion air humidifier and multi-stage condensate cleaning system to produce demineralized makeup water for the boiler and needed auxiliary systems and equipment. Näytä hankinnat »
Mainitut toimittajat: Radscan AB
2016-04-15   KYVO3, kattilalaitos (Lahti Energia Oy)
Lahti Energia Oy rakennuttaa Lahteen Kymijärven voimalaitosalueelle polttoaineteholtaan n. 170 MW monipolttoainevoimalaitoksen, jonka polttoaineina tulee olemaan puupohjainen biomassa ja turve sekä varapolttoaineena hiili. Tässä hankinnassa on kyse kiertoleijutekniikkaan (CFB) perustuvan kattilalaitoksen hankinnasta sisältäen kattila-apulaitteet sekä kattilalaitosrakennuksen. Näytä hankinnat »
Mainitut toimittajat: Amec Foster Wheeler Energia Oy
2015-06-02   Renewal of secondary air preheater in Joensuu Power Plant (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to renew a secondary air preheater to 199 MW (fuel) Power Plant in Joensuu, Finland. Power Plant's BFB boiler is biomass and peat fired. The purpose of the air preheater is to recover the heat from the boiler flue gas which increases the thermal efficiency of the boiler by reducing the useful heat lost in the flue gas. The present secondary air preheater manufactured by By-Cast origin from year 2000 is degraded and corroded. Delivery will be turn-key delivery. … Näytä hankinnat »
2015-02-25   Vantaan Energian Martinlaakson voimalaitoksen hiilikattilan typenoksidipäästöjen vähentäminen nro 113 (Vantaan Energia Oy)
Vantaan Energian Martinlaakson voimalaitoksen kivihiilipölypolttokattila on A. Ahlström Osakeyhtiön toimittama nurkkapolttoinen luonnonkiertokattila. Kattila K2 otettiin käyttöön vuonna 1982. Pääpolttoaine on venäläinen kivihiili. Martinlaakson K2:lla uusitaan nykyiset hiilipölypolttimet Low-NOx-tyyppisiin hiilipölypolttimiin. Polttimet ovat nurkkapolttimia ja sijaitsevat kolmessa tasossa. Polttimien vaihto tehdään 2016 kesäseisokin yhteydessä ja muutostyö tulee tehdä … Näytä hankinnat »
Mainitut toimittajat: Amec Foster Wheeler Energia Oy Eltel Networks Oy
2015-02-09   Pölypoltto (monipolttoaineinen) Hanneksenrinne (Seinäjoen Energia Oy)
Seinäjoen Energia Oy valitsee ensin ne yritykset, joille laskenta-asiakirjat annetaan. Valinta tehdään tässä hankintailmoituksessa esitetyillä perusteilla ja tehdystä valinnasta ilmoitetaan niille toimijoille, jotka on hyväksytty toimituksen tarjoajiksi. Osallsitumishakemukset tulee toimittaa Seinäjoen Energia Oy:lle 15.3.2015 mennessä. Osallistumishakemuksissa on ilmoitettava tässä ilmoituksessa edellytetyt tiedot. Osallsitumsihakemuksen tehneistä valitaan 2...3 Seinäjoen Energia Oy:lle soveltuvinta … Näytä hankinnat »
Mainitut toimittajat: Amec Foster Wheeler Energia Oy
2015-01-28   TSE: NA4 CHP-project — Water Treatment and Condensate Polishing Plant (Turun Seudun Energiantuotanto Oy)
Turun Seudun Energiantuotanto Oy builds a new combined heat and power unit (NA4) in an existing power plant area, where the company already owns three coal-fired power and CHP blocks (NA1, NA2 and NA3). Energy production of the new unit is based on wood- and agro-originated biomass, peat and coal. The CHP unit's nominal production rate will be 200 MWDH district heat and 50 MWth steam for industrial consumers from steam turbine extractions. The nominal fuel input is some 430 MWfuel and gross electric … Näytä hankinnat »
Mainitut toimittajat: Flootech Oy Vesi-Pauli Oy
2014-11-26   Hyötyvoimalan kattilamuutos 2015 (Kotkan Energia Oy)
Hyötyvoimalaitoksen perusparannus sisältäen mm. 3 kpl tulistinpakettien, mukaan lukien putkiston ja höyrystinpaketin uusinnan uudella konstruktiolla, jolla varmistetaan laitoksen parempi puhdistettavuus ja käytettävyys jatkossa. Urakan sisältö ja laajuus määritellään yksityiskohtaisesti tarjouspyynnön liitteenä olevissa kaupallisissa ja teknisissä asiakirjoissa. Näytä hankinnat »
Mainitut toimittajat: Amec Foster Wheeler Oy
2014-10-07   Wood pellet fired heat plant with auxiliary devices to Helsingin Energia Salmisaari Power Plant area (Helsingin Energia)
Background of the project: Existing oil fired heat boiler plant at Helsingin Energia Salmisaari Power Plant is at the end of its life cycle. It will not be revised but replaced by a new wood pellet fired heat boiler plant. Short description of the project: Procurement of wood pellet fired 100 MW (fuel) heat boiler plant is a turn-key delivery. Procurement includes fuel handling and flue gas cleaning systems as following. Fuel handling system is going to be integrated to existing power plants fuel … Näytä hankinnat »
Mainitut toimittajat: Valmet Technologies Oy
2014-08-29   49MW water tube heat boiler plant (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to build a LFO fired 49MW(fuel) hot water boiler plant in Joensuu, Finland. Final investment decision for the project is not yet made, it will be done after receiving the binding offers. The project is turn-key delivery for HOB plant with one light fuel oil fired 49MW water tube boiler and all the needed auxiliaries, piping works, electrification, automation and instrumentation to make boiler plant functional. Purchaser will be in charge for civil works (excavation, … Näytä hankinnat »
2014-07-01   Pellettipölylämpökeskus (Oy Turku Energia - Åbo Energi Ab)
Hankinta koskee noin 40 MW:n pellettipölylämpökeskuksen kokonaistoimitusta sisältäen pellettisiilot, pelletin jauhatuksen, pölypolttimet, vesikattilat, savukaasujen puhdistuksen, tuhkan poiston, apulaiteet, sähköistyksen, automaation, rakennustekniset työt, asennukset ja käyttöönotton. Tilaaja varaa oikeuden hankkia nämä hankinnat myös erillishankintana. Perustus- ja tonttityöt eivät sisälly hankintaan. Näytä hankinnat »
Mainitut toimittajat: Renewa Oy
2014-05-21   Naistenlahti Power Plant, Flue Gas Condensing Plant (Tampereen Energiantuotanto Oy)
Tampereen Energiantuotanto Oy is planning to built a flue gas condensing and heat recovery plant for district heat production to it's 200 MW (fuel) Naistenlahti power plant in Tampere, Finland. The power plant uses woodships and peat as fuel. The delivery consist of: — flue gas condensing equipment, — duct works from existing flue gas duct to flue gas condenser and to the stack including needed dampers, — flue gas booster fan, — condensate cleaning equipment, — building for flue gas condensing and … Näytä hankinnat »
Mainitut toimittajat: Valmet Power Oy
2014-05-15   Flue gas cleaning and heat recovery system (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to build a scrubber type flue gas cleaning and heat recovery system to it's 180 MW (fuel) Power Plant in Joensuu, Finland. Power Plant uses biomass and peat as fuel. Purpose of the flue gas cleaning and heat recovery system is primary to produce heat to the district heating network and secondary to reduce sulphur dioxide and dust emissions. Delivery will be turn-key delivery up from the foundation which is in purchaser's scope. If you are interested to participate to … Näytä hankinnat »
2014-03-31   Wood pellet conversion for two oil-fired boilers (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to convert two oil fired 52MW(fuel) hot water boilers for wood pellet fired boilers in heat boiler plant located in Espoo, Finland. Final investment decision is not yet made, it will be done after receiving the binding offers. The project is divided to three separate turn-key delivery packages (1. boiler rebuilt and fuel preparation, 2. pellet fuel handling system and 3. flue gas cleaning system) which will be offered separately and independently of each other. … Näytä hankinnat »
2014-02-26   Pellettipölykattilalaitoshankinta (Hyvinkään Lämpövoima Oy)
Hankinta koskee noin 10 MW:n pellettipölykattilalaitoksen kokonaistoimitusta sisältäen pellettisiilot, pelletin jauhatuksen, pölypolttimen, vesikattilan, tuhkan poiston, apulaiteet, sähköistyksen, automaation, rakennustekniset työt, asennukset ja käyttöönotton. Tilaaja varaa oikeuden hankkia nämä hankinnat myös erillishankintana. Perustus- ja tonttityöt eivät sisälly hankintaan. Näytä hankinnat »
Mainitut toimittajat: KPA Unicon Oy
2014-01-14   Air Heater elements replacement at Naantali Power Plant Boiler 3 (315 MWth) (Fortum Power and Heat Oy)
Air Heater elements replacement for TSE Oy owned and Fortum Power and Heat Oy operated Naantali Power Plant Boiler no. 3. Delivery scope will contain a delivery of new elements includung dismantling and installation work at the Power Plant. Boiler and Air Heater: Boiler type: Sulzer 0.006.051, Boiler capacity: 430t/h , 318MWth Fuel : Bituminous coal, LHV=26,8MJ/kg, ash ≤15,0%, S ≤1,0% Boiler will be equipped with SCR process in 2015 which need be taken into account in the selection of element … Näytä hankinnat »