2023-06-06Pre-qualification for turnkey delivery of electric boiler to Nuijala heat station (Fortum Power and Heat Oy)
Fortum is planned to invest in Nuijala, Espoo with a new approx. 50-60 MW electric boiler, a 20,000 m3 district heat accumulator and DH pumping systems (the “Plant”). The Plant will store, produce, and deliver heat to Fortum district heating network in Espoo and Kirkkonummi. The Plant is designed to be operated remotely from the main control room at Suomenoja power plant (approx. 10 km from the Nuijala Plant). However, there will be a small local control room at the Plant for commissioning, start-up, …
Näytä hankinnat »
2023-06-01Pre-qualification for the turnkey delivery of accumulator to Nuijala heat station (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning a greenfield project in Nuijala Espoo and this pre-qualification is one of the main equipment which will be purchased to the site.
Fortum Power and Heat Oy wishes to obtain a turnkey delivery of a new hot water district heat accumulator of 20 000 m3. The district heat accumulator will be unpressurized steel tank type and the maximum operation temperature is 98°C. Design temperature 100°C. The top of the tank is equipped with a steam blanket blocking the air to get …
Näytä hankinnat »
2023-03-13E-HOUSE for Mankkaa CHC-plant (Fortum Power and Heat Oy)
Fortum is building CHC (Combined Heating and Cooling)-plant in Espoo, Mankkaa.
As a part of the project, E-House-delivery is needed. The delivery consist of prefabricated E-House container-module or modules including all the necessary electrical components regarding to power distribution for the plant.
Preliminary technical description shall be published in Buyer's SAP Ariba-portal.
Näytä hankinnat »
2023-01-30RENEWAL OF ECONOMIZER TO KIVENLAHTI BIO-HEATING PLANT, ESPOO FINLAND (Fortum Power and Heat Oy)
Turnkey delivery of economizer to Kivenlahti bio-heating plant.
Kivenlahti K4-boiler was commissioned in 2020. The fuel power of the boiler is 49 MW. The fuel is solid wood fuels which consist of recycled wood, forest biomass (forest residues, hard wood chips) and industrial by-products (bark, saw dust). The boiler produces heat to the district heating network of Espoo. The boiler is connected to the district heating network with a heat exchanger. The boiler is a water boiler equipped with a stream drum. …
Näytä hankinnat »
2022-12-13Heat Pump Module (Fortum Power and Heat Oy)
Fortum Power and Heat Oy (the Purchaser) is planning to implement water-to-water heat pump (WWHP) plant to Mankkaa, Espoo, Finland. WWHP plant will produce cooling to local fluid network and heating to Fortum’s district heating (DH) networks.
We kindly ask interested bidders to submit application to participate tendering process of Heat Pump modules that have 3500 kW of cooling capacity in full scale. 3/4 of capacity will be installed at once and 1/4 of capacity later as an expansion into the …
Näytä hankinnat » Mainitut toimittajat:Oilon Oy
2022-11-17Invitation to Tender for Electrification for Karaportti 3,5 MW AWHP plant, Espoo Finland (Fortum Power and Heat Oy)
The scope of works is the turn-key delivery for the electrification of the AWHP plant within the scope of supply and delivery limits specified in the Appendices.
More detailed scope of the Works, Delivery Limits and other optional works are discussed in Appendix 3 and its sub-appendices.
Site is located at the address Karaportti 02610 Espoo, Finland,
The delivery shall include complete design, engineering, procurement, manufacturing, quality control, seaworthy packaging, transportation and forwarding to …
Näytä hankinnat »
2022-10-10Electrification for Karaportti 3,5 MW AWHP plant, Espoo (Fortum Power and Heat Oy)
The scope of works is the turn-key delivery for the electrification of the AWHP plant within the scope of supply and delivery limits specified in the Appendices.
More detailed scope of the Works, Delivery Limits and other optional works are discussed in appendices.
Site is located at the address Karaportti 02610 Espoo, Finland,
The delivery shall include complete design, engineering, procurement, manufacturing, quality control, seaworthy packaging, transportation and forwarding to the site, erection and …
Näytä hankinnat »
2022-05-13CHC Heat Pumps (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to build a new
modular CHC (combined heat and cooling) heat pump plant in Espoo, Finland. Heat pumps will produce heating and cooling to Fortum’s heating and cooling networks.
WWHP (water-to-water heat pump) plant will produce 3-5 MW cooling for DC networks. Supplier should propose suitable heat pumps which provide cooling to the DC network and supply heat to the DH network.
Näytä hankinnat »
2022-03-30Modular Heat Pump - Espoo, Finland (Fortum Power and Heat Oy)
Fortum Power and Heat Oy (the Purchaser) is planning to develop a modular heat pump concept for producing district heating. The first heat pump module(s) will be located at Espoo, Finland. Later, the module(s) may be transported and coupled to a bigger heat pump plant as one module of many.
Supplier need to deliver a Modular Heat Pump setup which has at least 3500 kW of cooling capacity (in one or several heat pump modules). Heat pump module is a complete functioning unit which includes all the necessary …
Näytä hankinnat »
2022-01-18Aalto Works 2 Heat Pumps - Prequalification (Fortum Power and Heat Oy)
Fortum Power and Heat Oy (the Purchaser) is planning to expand an existing air to water heat pump (AWHP) plant in Espoo. AWHP plant will produce heating and cooling to Fortum’s low temperature local area heating (LAH) and local area cooling (LAC) networks. The plant is located in Otaniemi (Espoo, Finland) on the plot which has already Fortum’s heat only boiler (HOB) plant.
This request will work as invitation for the first phase of the procurement. We kindly ask interested bidders to submit application …
Näytä hankinnat »
2021-11-12Prequalification of turnkey delivery for electric boiler to Suomenoja power plant (Fortum Power and Heat Oy)
With this request, Fortum Power and Heat Oy wishes to obtain a turnkey delivery for an agreement for the supply of a appox. 50MW new electrode boiler with an associated expansion system, boiler circuit pump, control valves and heat exchanger for Suomenoja heat production facility. The scope will include complete design, engineering, manufacturing, installation, commissioning and training of the Purchaser’s operating and maintenance personnel. General plant and process design and engineering as well as …
Näytä hankinnat »
2021-05-06Vermo 2 Indoor Heat Pump Pre-qualification (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to implement an air-to-water heat pump (AWHP) plant to Vermo (Espoo, Finland). The AWHP plant will produce appr. 10 MW heating and appr. 8 MW cooling to Fortum’s district heating (DH) and cooling (DC) networks. The plant will be located in Vermo on the plot which has already Fortum’s heating plant.
The AWHP plant will have two different kind of heat pumps:
Pos 1: Outdoor installed heat pumps which take heat from the outside air and supply heat to an intermediate …
Näytä hankinnat » Mainitut toimittajat:Oilon Oy
2021-05-06Vermo 2 Outdoor Heat Pump Pre-qualification (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to implement an air-to-water heat pump (AWHP) plant to Vermo (Espoo, Finland). The AWHP plant will produce appr. 10 MW heating and appr. 8 MW cooling to Fortum’s district heating (DH) and cooling (DC) networks. The plant will be located in Vermo on the plot which has already Fortum’s heating plant.
The AWHP plant will have two different kind of heat pumps:
Pos 1: Outdoor installed heat pumps which take heat from the outside air and supply heat to an intermediate …
Näytä hankinnat »
2020-10-02Pre-Qualification Top Level Automation System Supply for ESPOO District Heating System (Fortum Power and Heat Oy)
Fortum Heating and Cooling has launched an End-to-end (E2E) transformation program to enable the development of district heating system to meet the strategic objectives of reaching the climate goals of eliminating CO2 emissions.
Regard to E2E, Fortum is looking for supplier for the top level automation project, the automated steering of plants and network which comprises an update of the upper layer of the automation of the district heating system from a traditional Supervisory Control and Data …
Näytä hankinnat »
2020-06-01Request for Information — Technical Consulting Services (Fortum Power and Heat Oy)
Fortum is looking for consultants that can strengthen our performance in investment projects and to some extent also in our daily operations. The consultant's general area of competence should be of a technical nature, with special focus having experience providing technical consulting services within Fortum’s business areas such as heating and cooling, heat pumps, solar, wind, hydro, nuclear power, automation and control systems, general civil work management, mechanical engineering, electrical …
Näytä hankinnat »
2019-12-17Lasikuituputkiurakka (Finnoo III-projekti) (Fortum Power and Heat Oy)
Lasikuituisten vedensiirtoprosessiputkien valmistaminen, toimitukset ja asennukset kannakkeille.
Osallistumishakemus täytetään kohdan I.3) linkistä avautuvassa hankitaportaalissa. Osallistumishakemus on jätettävä pyydettyine liitteineen 7.1.2020 klo 16:00 mennessä.
Näytä hankinnat »
2019-07-03Tendering of Metering Equipment for District Heating Networks (Fortum Power and Heat Oy)
The object relates to a Framework Agreement with the Fortum Power and Heat Oy (Fortum) Group for the Customer’s purchase of metering equipment and its accessories installed underground, indoors and in tunnels for Fortum’s distribution of district heating and cooling. Target to establish national Frame Agreements locally.
Näytä hankinnat »
2019-05-17Industrial Sewage Heat Pump (Fortum Power and Heat Oy)
Treated sewage industrial heat pump with the output of 20-25 MW to be located in purchaser's existing Suomenoja heat pump plant to serve the heat production for purchaser's district heating network in Espoo, Finland.
To apply the participation to tendering please open the web link defined in Chapter I.3) sign in and fill in required information for Tenderer's Minimum Requirements by 7.6.2019 at 16:00.
Näytä hankinnat » Mainitut toimittajat:Friotherm AG
2017-06-26Ilmasuuttimien uusinta ja painerungon muutostyöt naantalin voimalaitoksen 3-kattilalla (Fortum Power and Heat Oy)
Urakka käsittää seuraavat toimenpiteet Naantalin voimalaitoksen 3-kattilalle:
1. Hiilipölypolttimien ilma- ja OFA-suuttimien esivalmistus, purku ja asennus varusteineen.
2. Tulipesän hiilipöly-, öljy-, OFA-suuttimien ja liekinvalvojien väistöputkien esivalmistus, purku ja asennus varusteineen.
3. Hiilipölypolttimien liekinvalvojien asennusosien esivalmistus, purku asennusosia varten ja mekaaninen asennus varusteineen.
Työn toteutus kesäseisokissa 2018.
Näytä hankinnat »
2016-10-20Kaukolämpöverkkorakentamisen vuosiurakat (Fortum Power and Heat Oy)
Kaukolämpö- ja kaukokylmäverkoston liittymä- ja ylläpitorakentaminen Fortum Power and Heat Oy:n verkkoalueilla urakka-aikana 1.4.2017 – 31.3.2019. Lisäksi sopimus sisältää mahdollisuuden 2 x 2 vuoden optiokausiin.
Urakka-alueita on kolme:
1. Espoo (Espoo, Kauniainen ja Kirkkonummi);
2. Keski-Uusimaa (Tuusula ja Järvenpää);
3. Joensuu.
Urakka-alueet jaetaan kolmeen erillisurakkaan:
A. Maanrakennustyöt (urakka-alueet 1-3);
B. Putkityöt (urakka-alueet 1-2);
C. Eristystyöt (urakka-alueet 1-2).
Näytä hankinnat » Mainitut toimittajat:Maalinja OyPaajanti OyTurun Asennus ja Luokkahitsarit Oy
2015-09-21Fuel Handling System for special solid bio fuel (horse manure) (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is starting a project to use horse manure as partial fuel in the Power Plant of Järvenpää, Finland. For this we need a Fuel Handling System which scope includes 200 m³ silo for horse manure fuel storing, conveyors and screws capacity of 5-50 m³/h needed for fuel feeding, and included also needed accessories such as instruments and electric motors. Installation and commissioning is also in supplier's scope. On purchaser's responsibility stays civil works, electrification and …
Näytä hankinnat »
2015-07-10Renewal of district heat exchangers in Joensuu Power Plant (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to renew a district heat exchangers to 199 MW (fuel) CHP Power Plant in Joensuu, Finland. Power plant delivers district heat to city of Joensuu. In Joensuu Power Plant there is a two straight tube model district heat exchangers, which maximum capacity is 120 MW. District heat water is in tube side and maximum operating values are 16 bar and 130 °C. In shell-side heat transfer medium is low pressure steam that is coming from steam turbine, maximum operating values are …
Näytä hankinnat » Mainitut toimittajat:Sahala Works Oy
2015-06-02Renewal of secondary air preheater in Joensuu Power Plant (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to renew a secondary air preheater to 199 MW (fuel) Power Plant in Joensuu, Finland. Power Plant's BFB boiler is biomass and peat fired. The purpose of the air preheater is to recover the heat from the boiler flue gas which increases the thermal efficiency of the boiler by reducing the useful heat lost in the flue gas. The present secondary air preheater manufactured by By-Cast origin from year 2000 is degraded and corroded.
Delivery will be turn-key delivery. …
Näytä hankinnat »
2015-04-08Puupellettien kuljetuspalvelu (Fortum Power and Heat Oy)
Fortum on muuttamassa Espoon Kivenlahden lämpölaitoksensa käyttämään puupellettejä ja etsii kumppaniksi kuljetusliikettä pellettien kuljettamiseksi Inkoon sataman varastosta Kivenlahteen.
Käyttö alkaa suunnitelman mukaan marraskuussa 2015. Arvioitu pellettien käyttömäärä ja kuljetusmäärä on vuositasolla pienimmillään noin 10 000 t / 17 000 irto-m³ ja suurimmillaan jopa noin 85 000 t / 140 000 irto-m³. Pelletiä käytetään enimmillään viikossa n. 3 200 t. Pääosa käytöstä ja kuljetustarpeesta on lokakuun …
Näytä hankinnat » Mainitut toimittajat:Karjaan Kuorma-Autokeskus Oy
2015-01-23District heating water accumulator tank 5 000 m (Fortum Power and Heat Oy)
Fortum Power and Heat Oy will build a District Heat Accumulator in Järvenpää Power Plant in Finland. Scope of the delivery will be a 5 000 m district heating water accumulator tank made of carbon steel including planning, materials, delivery, installation and thermal insulation of the tank. Purchaser will be responsible for building the foundation to the tank. Exact specification and delivery limits of the tank will be defined in the Purchase Request.
Näytä hankinnat »
2014-08-2949MW water tube heat boiler plant (Fortum Power and Heat Oy)
Fortum Power and Heat Oy is planning to build a LFO fired 49MW(fuel) hot water boiler plant in Joensuu, Finland. Final investment decision for the project is not yet made, it will be done after receiving the binding offers.
The project is turn-key delivery for HOB plant with one light fuel oil fired 49MW water tube boiler and all the needed auxiliaries, piping works, electrification, automation and instrumentation to make boiler plant functional. Purchaser will be in charge for civil works (excavation, …
Näytä hankinnat »