2021-06-14Rewinding or Replacement of Stator of 233.3 MVA Turbogenerator (Jyväskylän Voima Oy)
The procurement concerns to the rewinding or the replacement of the generator stator of the Keljonlahti power plant, owned and operated by Jyväskylän Voima Oy, Jyväskylä, Finland.
Alternative 1, Rewinding of the generator stator:
The rewinding is to be done on site.
The scope of the supply of the contractor contains all necessary works, materials and services like producing the new winding bars, disassembly of the generator unit for rewinding, removal of the existing stator windings, conditioning of the …
Näytä hankinnat » Mainitut toimittajat:Empower IN Oy
2018-11-29Keljonlahti steam turbine overhaul in Jyväskylä, Finland (Jyväskylän Voima Oy)
Jyväskylän Voima Oy is operating Keljonlahti CHP power plant in Jyväskylä, Finland. Keljonlahti. Plant started its operations in 2010. Turbine has been manufactured by LMZ in St. Petersburg, Russia and commissioned in 2010. The turbine is a triple casing, extraction-condensing. The unit has currently more than 41000 h of operation time. Total numbers of start up are 43. Scope of delivery shall include the major overhaul works for Keljonlahti steam turbine. In general, overhaul works are:
1) turbine …
Näytä hankinnat » Mainitut toimittajat:Fortum Power and Heat Oy, Power Solutions
2011-08-29Kivihiilen kuljetin- ja käsittelylaitteet (Jyväskylän Voima Oy)
Jyväskylän Voima Oy suunnittelee Keljonlahden polttoainevalikoiman laajentamista kivihiilellä. Kivihiili tuotaisiin voimalaitosalueelle junalla. Projekti on suunniteltu toteutettavaksi kahtena osakokonaisuutena, joiden yhteensovituksesta ja aikataulukoordinoinnista vastaa Jyväskylän Voima Oy. Hankittavat osakokonaisuudet ovat:
Kivihiilen kuljetin- käsittelylaitteet (tämä ilmoitus).
Kivihiililaitteiden maanrakennus- ja perustusurakka (ilmoitetaan myöhemmin).