Tampereen Sähkölaitos Oy is building a new CFB boiler plant to replace existing 200 MW NSL2 BFB boiler combusting forest biomass and peat plant in Naistenlahti, Tampere. The Purchaser will also renew the power plant’s solid fuel reception, screening, storage and conveyor equipment, as well as other necessary systems serving the new boiler plant. The Purchaser is named the project NSL3. This Contract Notice is published to purchase NSL3 FGTC (Flue Gas Tube Condenser and Condensate Treatments). The Supply consisting of the full process delivery of the flue gas tube condenser and condensate treatment systems containing all necessary auxiliary equipment, piping, instrumentation, electrification and cabling within the scope of the delivery.
Määräaika
Tarjousten vastaanottamisen määräaika oli 2022-05-02.
Hankinta julkaistiin 2022-04-13.
hankintailmoitus (2022-04-13) Kohde Hankinnan laajuus
Otsikko: Lämmön talteenottojärjestelmät
Viitenumero: NSL3-T101
Lyhyt kuvaus:
Tampereen Sähkölaitos Oy is building a new CFB boiler plant to replace existing 200 MW NSL2 BFB boiler combusting forest biomass and peat plant in Naistenlahti, Tampere. The Purchaser will also renew the power plant’s solid fuel reception, screening, storage and conveyor equipment, as well as other necessary systems serving the new boiler plant. The Purchaser is named the project NSL3.
This Contract Notice is published to purchase NSL3 FGTC (Flue Gas Tube Condenser and Condensate Treatments). The Supply consisting of the full process delivery of the flue gas tube condenser and condensate treatment systems containing all necessary auxiliary equipment, piping, instrumentation, electrification and cabling within the scope of the delivery.
Tampereen Sähkölaitos Oy is building a new CFB boiler plant to replace existing 200 MW NSL2 BFB boiler combusting forest biomass and peat plant in Naistenlahti, Tampere. The Purchaser will also renew the power plant’s solid fuel reception, screening, storage and conveyor equipment, as well as other necessary systems serving the new boiler plant. The Purchaser is named the project NSL3.
This Contract Notice is published to purchase NSL3 FGTC (Flue Gas Tube Condenser and Condensate Treatments). The Supply consisting of the full process delivery of the flue gas tube condenser and condensate treatment systems containing all necessary auxiliary equipment, piping, instrumentation, electrification and cabling within the scope of the delivery.
Ilmoituksen metatiedot
Alkukieli: englanti 🗣️
Asiakirjatyyppi: hankintailmoitus
Sopimuksen luonne: Tavarat
Asetus: Euroopan unioni
Yhteinen hankintanimikkeistö (CPV)
Koodi: Lämmön talteenottojärjestelmät📦
Lisä-CPV-koodi: Jätevedenkäsittelylaitteet📦 Suorituspaikka
NUTS-alue: Pirkanmaa
🏙️
Menettely
Menettelyn tyyppi: Neuvottelumenettely
Tarjouksen tyyppi: Tarjous koskee kaikkia eriä
Myöntämisperusteet
Kokonaistaloudellisesti edullisin tarjous
Tampereen Sähkölaitos Oy is building a new CFB boiler plant to replace existing 200 MW NSL2 BFB boiler combusting forest biomass and peat plant in Naistenlahti, Tampere. The Purchaser will also renew the power plant’s solid fuel reception, screening, storage and conveyor equipment, as well as other necessary systems serving the new boiler plant. The Purchaser is named the project NSL3.
Tampereen Sähkölaitos Oy is building a new CFB boiler plant to replace existing 200 MW NSL2 BFB boiler combusting forest biomass and peat plant in Naistenlahti, Tampere. The Purchaser will also renew the power plant’s solid fuel reception, screening, storage and conveyor equipment, as well as other necessary systems serving the new boiler plant. The Purchaser is named the project NSL3.
This Contract Notice is published to purchase NSL3 FGTC (Flue Gas Tube Condenser and Condensate Treatments). The Supply consisting of the full process delivery of the flue gas tube condenser and condensate treatment systems containing all necessary auxiliary equipment, piping, instrumentation, electrification and cabling within the scope of the delivery.
This Contract Notice is published to purchase NSL3 FGTC (Flue Gas Tube Condenser and Condensate Treatments). The Supply consisting of the full process delivery of the flue gas tube condenser and condensate treatment systems containing all necessary auxiliary equipment, piping, instrumentation, electrification and cabling within the scope of the delivery.
Kesto: 17 kuukautta Suorituspaikka
Pääkohde tai suorituspaikka: Tampere, Naistenlahti power plant
Oikeudelliset, taloudelliset, rahoitukselliset ja tekniset tiedot Osallistumisehdot
Kelpoisuus harjoittaa ammattitoimintaa: All conditions for participation are presented in ESPD.
Sopimuksen toteuttaminen
Sopimuksen täytäntöönpanoehdot:
Condition for signing and entering into force of the contract is that the board of directors of Tampereen Sähkölaitos Oy will make a positive investment decision.
Menettely
Oikeusperusta: 32014L0025
Ehdokkaiden vähimmäismäärä: 3
Ehdokkaiden enimmäismäärä: 5
Objektiiviset kriteerit rajoitetun ehdokasjoukon valitsemiseksi: Resources of Contracting Entity
Tarjousten vastaanottoaika: 12:00
Kielet, joilla tarjoukset tai osallistumishakemukset voidaan jättää: englanti 🗣️
The contracting entity decides to suspend the procurement according to section 116 of the Act on the Procurement and Concession Contracts of Units Operating in the VVater and Energy Supply, Transport and Postal…
… Services.
The reason for suspending the procurement is, that during the procurement process it has become apparent to the contracting entity that the original schedule for both the procurement process and the delivery must be amended considerably. Therefore, the original procurement documents need to be considerably amended to the extent that suspending the procurement and re-tendering the procurement contract is necessary.
The need to amend the schedule of the procurement process and the supply time is due to two reasons. Firstly, the delivery times for other procurements related to the same project have been significantly extended from the original pian, and consequently, the contracting entity must redesign the overall implementation schedule for the project. Secondly, the funding decision of the Ministry of Employment and the Economy will not be received according to the original schedule during May-June, 2022. Due to this, the Board of Directors of Tampereen Sähkölaitos Oy cannot make an investment decision according to the original schedule. At this time the contracting entity does not have the necessary information to set out a new procurement process and delivery schedule, but it is expected that the needed delay will be at least a couple of months.
The contracting entity will re-tender NSL3 FGTC (NSL3-T101) as a public contract. The estimated time for the new procurement process is autumn 2022.
… Services.
The reason for suspending the procurement is, that during the procurement process it has become apparent to the contracting entity that the original schedule for both the procurement process and the delivery must be amended considerably. Therefore, the original procurement documents need to be considerably amended to the extent that suspending the procurement and re-tendering the procurement contract is necessary.
The reason for suspending the procurement is, that during the procurement process it has become apparent to the contracting entity that the original schedule for both the procurement process and the delivery must be amended considerably. Therefore, the original procurement documents need to be considerably amended to the extent that suspending the procurement and re-tendering the procurement contract is necessary.
The need to amend the schedule of the procurement process and the supply time is due to two reasons. Firstly, the delivery times for other procurements related to the same project have been significantly extended from the original pian, and consequently, the contracting entity must redesign the overall implementation schedule for the project. Secondly, the funding decision of the Ministry of Employment and the Economy will not be received according to the original schedule during May-June, 2022. Due to this, the Board of Directors of Tampereen Sähkölaitos Oy cannot make an investment decision according to the original schedule. At this time the contracting entity does not have the necessary information to set out a new procurement process and delivery schedule, but it is expected that the needed delay will be at least a couple of months.
The need to amend the schedule of the procurement process and the supply time is due to two reasons. Firstly, the delivery times for other procurements related to the same project have been significantly extended from the original pian, and consequently, the contracting entity must redesign the overall implementation schedule for the project. Secondly, the funding decision of the Ministry of Employment and the Economy will not be received according to the original schedule during May-June, 2022. Due to this, the Board of Directors of Tampereen Sähkölaitos Oy cannot make an investment decision according to the original schedule. At this time the contracting entity does not have the necessary information to set out a new procurement process and delivery schedule, but it is expected that the needed delay will be at least a couple of months.
The contracting entity will re-tender NSL3 FGTC (NSL3-T101) as a public contract. The estimated time for the new procurement process is autumn 2022.