This insulation delivery includes the following systems:
— high pressure steam system (main steam: design temperature 565 'C, hot reheat and cold reheat systems including for example pipe size DN 700),
— reduction steam system (line DN 1400 including noise insulation),
— district heating system, including e.g. pipe size DN 700,
— bleed steam lines by steam turbine and other low and medium pressure steam systems,
— heavy fuel oil system,
— condensate system,
— spray water system,
— drain systems and low/medium pressure steam headers of the blowdown tank,
— pipe bridge piping (insulation and covering on the bridge),
— tie-in insulations to existing systems,
— other lines and equipment will be specified in call for tender to selected suppliers Pori Energia Oy has awarded Pöyry Finland Oy for EPCM consultant.
Määräaika
Tarjousten vastaanottamisen määräaika oli 2019-02-07.
Hankinta julkaistiin 2019-01-23.
Toimittajat
Seuraavat toimittajat mainitaan hankintapäätöksissä tai muissa hankinta-asiakirjoissa:
Kohde Hankinnan laajuus
Otsikko: Insulation
101007990-F0070
Tuotteet/palvelut: Lämpöeristeet📦
Lyhyt kuvaus:
“This insulation delivery includes the following systems:
— high pressure steam system (main steam: design temperature 565 'C, hot reheat and cold reheat...”
Lyhyt kuvaus
This insulation delivery includes the following systems:
— high pressure steam system (main steam: design temperature 565 'C, hot reheat and cold reheat systems including for example pipe size DN 700),
— reduction steam system (line DN 1400 including noise insulation),
— district heating system, including e.g. pipe size DN 700,
— bleed steam lines by steam turbine and other low and medium pressure steam systems,
— heavy fuel oil system,
— condensate system,
— spray water system,
— drain systems and low/medium pressure steam headers of the blowdown tank,
— pipe bridge piping (insulation and covering on the bridge),
— tie-in insulations to existing systems,
— other lines and equipment will be specified in call for tender to selected suppliers Pori Energia Oy has awarded Pöyry Finland Oy for EPCM consultant.
Näytä lisää
Arvioitu arvo ilman arvonlisäveroa: EUR 850 000 💰
1️⃣
Suorituspaikka: Satakunta🏙️
Hankinnan kuvaus:
“Pori Energia Oy is investing for new biomass power plant in Aittaluoto. The construction of the new power plant will be completed by mid-2020 and once in...”
Hankinnan kuvaus
Pori Energia Oy is investing for new biomass power plant in Aittaluoto. The construction of the new power plant will be completed by mid-2020 and once in operation it will replace some of the boiler capacity at Aittaluoto. Capacity of the boiler will be around 90 MW and it will supply heat to the city of Pori, process steam to neighboring industrial clients and power to the grid. The new plant uses biofuels, peat and can also use solid recovered fuel (SRF). The supply shall preliminary consist of (but not limited to):
scope of works includes:
— all needed materials and installation works for insulation/covering will be specified in Call for tender for selected suppliers,
— insulation/covering of pipes and pipe parts (including e.g. bends, elbows, reducers, T-pieces, condensate pocekts) material,
— insulation of process tanks,
— insulation of piping related equipment, e.g. pumps, valves, flow elements, heat exchangers, and silencers,
— high/low pressure preheaters,
— district heating heat exchangers,
— possible wall/roof penetrations,
— possible anti-condensation insulation,
— scaffolding,
— all needed documentation.
Note: Insulation standards will be specified in the enquiry. Detailed description of the work will be handed for the selected bidders fulfilling the minimum criteria mentioned in this Contract Notice.
Näytä lisää Myöntämisperusteet
Hinta
Sopimuksen, puitesopimuksen tai dynaamisen hankintajärjestelmän kesto
Jäljempänä oleva aikataulu on ilmaistu kuukausina.
Kuvaus
Kesto: 8
Oikeudelliset, taloudelliset, rahoitukselliset ja tekniset tiedot Osallistumisehdot
Luettelo ja lyhyt kuvaus olosuhteista:
“Pori Energia is entitled to exclude a Candidate that does no meet the criteria set forth below, or gives false information to Pori Energia.
1) The Candidate...”
Luettelo ja lyhyt kuvaus olosuhteista
Pori Energia is entitled to exclude a Candidate that does no meet the criteria set forth below, or gives false information to Pori Energia.
1) The Candidate or a person having representation, decision-making or supervisory rights with respect to the Candidate, as well as the subcontractors used by the Candidate, have not been declared guilty in offences of corruptive nature, infraudulent actions in financial matters, in money laundering or participation in criminal organization by a valid court judgement that appears from the criminal record;
2) The Candidate has not been declared insolvent, its business activities have not been suspended or discontinued or legal proceedings have not been started on the Candidate’s bankruptcy or it has not been found out that up to the expected completion date of the contract the Candidate is going to be liquidated;
3) The Candidate does not have tax or state compulsory social insurance payment debts in Finland or in another country where it is registered or in the country of its residence;
4) The Candidate is registered to the Trade Register, Commercial register or equal register of its country of incorporation:
— copy of the registration certificate issued by the relevant institution in Finland or the country of the Candidate’s incorporation must be submitted. Contractor’s Obligations and Liability will be checked and it must be fulfilled before contract can be signed (According to the Act 1233/2006). If the Candidate is a consortium, each member of the consortium shall fulfill these general criteria. Also possible subcontractors shall fulfill such criteria.
Näytä lisää Taloudellinen ja rahoituksellinen asema
Luettelo ja lyhyt kuvaus valintaperusteista:
“Criteria(s) to be fulfilled:
— the company's turnover need to be at least four million euros (4 000 000 EUR) during the last 3 years. In addition, the...”
Luettelo ja lyhyt kuvaus valintaperusteista
Criteria(s) to be fulfilled:
— the company's turnover need to be at least four million euros (4 000 000 EUR) during the last 3 years. In addition, the cumulative operating income must be at least two (2) % of the cumulative turnover over the last 3 years.
Document(s) to be submitted:
— statement signed by the Candidate concerning the average financial turnover of the Candidate excluding VAT for the period of last three (3) financial years (2015, 2016 and 2017/3 latest financial years of the Candidate. Candidates that have been established later shall submit the aforementioned documents for the period of operation,
— financial statements of the Candidate for the period of last three (3) financial years (2015, 2016 and 2017/3 latest financial years of the Candidate. Candidates that have been established later shall submit the aforementioned documents for the period of operation. The Contracting Entity reserves the right to make a credit risk control checking from a solid corporation e.g Suomen Asiakastieto, Bisnode or similar and if the risk value is bigger than 2, the candidate can be excluded.
Näytä lisää Tekninen ja ammatillinen pätevyys
Luettelo ja lyhyt kuvaus valintaperusteista:
“1) Minimum Reference Requirement: These references refer to the minimum references which affect the selection of the candidates. The candidate must have...”
Luettelo ja lyhyt kuvaus valintaperusteista
1) Minimum Reference Requirement: These references refer to the minimum references which affect the selection of the candidates. The candidate must have experience during the last five (5) years (6/2013 — 6/2018) of deliveries from similar power plant piping installation and under similar conditions than in this acquisition (including full responsibility for engineering, manufacture, installation and commissioning per reference) that have been taken into commercial operation and fulfill the norms and standards;
2) The candidate must have a valid certified quality assurance system (ISO-9001 or equivalent);
3) Comparative References: These references refer to non-minimum references which affect the candidate comparison and must be different references than those indicated by the candidate to meet the minimum reference requirements (Evaluation Point 1). The experience of the candidate without time constraints of deliveries of sub-processes from similar power plant piping and under similar conditions than in this acquisition (including full responsibility for engineering, manufacture, installation and commissioning per reference) that have been taken into commercial operation. The total number of the references of the candidate are taken into account in the comparison, provided that the reference contains a district heating/power plant piping and that at least one of the requirements listed below is met (they must be different references than the candidate has indicated to meet the minimum reference requirements (evaluation point 1)). The equivalence and number of references are evaluated based on the written report submitted by the candidate. The candidate must complete the reference form attached to the procurement notice (Appendix 2).
Näytä lisää Osallistumisehdot
Vaadittavat vakuudet ja takuut: Will be specified in call for tenders.
Tärkeimmät rahoitusehdot ja maksujärjestelyt ja/tai viittaus niitä koskeviin säännöksiin: Will be specified in call for tenders.
Menettely Toimenpiteen tyyppi
Neuvottelumenettely, johon liittyy edeltävä kilpailuttaminen
Hallinnolliset tiedot
Tarjousten tai osallistumishakemusten vastaanottamisen määräaika: 2019-02-07
13:00 📅
Kielet, joilla tarjoukset tai osallistumishakemukset voidaan jättää: englanti 🗣️
Kielet, joilla tarjoukset tai osallistumishakemukset voidaan jättää: suomi 🗣️
Jäljempänä oleva aikataulu on ilmaistu kuukausina.
Vähimmäisaika, jonka kuluessa tarjoajan on pidettävä tarjous voimassa: 3
Kohde Hankinnan laajuus
Lyhyt kuvaus:
“This insulation delivery includes the following systems:
— high pressure steam system,
— reduction steam system (including noise insulation),
— district...”
Lyhyt kuvaus
This insulation delivery includes the following systems:
— high pressure steam system,
— reduction steam system (including noise insulation),
— district heating system,
— bleed steam lines by steam turbine and other low and medium pressure steam systems,
— fuel oil system,
— condensate system,
— spray water system,
— drain systems and low/medium pressure steam headers of the blowdown tank,
— pipe bridge piping (insulation and covering on the bridge),
— tie-in insulations to existing systems,
— other lines and equipment will be specified in call for tender to selected suppliers Pori Energia Oy has awarded Pöyry Finland Oy for EPCM consultant.
Näytä lisää
Hankinnan kokonaisarvo (ilman arvonlisäveroa): EUR 422 705 💰
Kuvaus
Hankinnan kuvaus:
“Pori Energia Oy is investing for new biomass power plant in Aittaluoto. The construction of the new power plant will be completed by mid-2020 and once in...”
Hankinnan kuvaus
Pori Energia Oy is investing for new biomass power plant in Aittaluoto. The construction of the new power plant will be completed by mid-2020 and once in operation it will replace some of the boiler capacity at Aittaluoto. Capacity of the boiler will be around 90 MW and it will supply heat to the city of Pori, process steam to neighboring industrial clients and power to the grid. The new plant uses biofuels, peat and can also use solid recovered fuel (SRF). Scope of works includes:
— all needed materials and installation works for insulation/covering will be specified in call for tender for selected suppliers,
— insulation/covering of pipes and pipe parts (including e.g. bends, elbows, reducers, T-pieces, condensate pockets) material,
— insulation of process tanks,
— insulation of piping related equipment, e.g. pumps, valves, flow elements, heat exchangers, and silencers,
— district heating heat exchangers,
— scaffolding.