Further information about the procedure and the schedule
The innovation partnership contract award procedure has the following steps (estimated schedule presented in parenthesis):
1) the contract notice and the invitation to participate (This document):
• the contracting authority publishes the contract notice, the invitation to participate, the preliminary invitation to negotiate and the preliminary invitation to tender,
• the Candidates submit to the Contracting Authority the questions concerning the invitation to participate (25 May 2020),
• the Contracting Authority publishes the answers to the above-mentioned questions (by 29 May 2020),
• the Candidates submit the applications to participate (16 June 2020);
2) the selection of Tenderers to the negotiations, the invitation to negotiate and the preliminary invitation to tender:
• the Contracting Authority selects Tenderers for negotiation stage among the Candidates that have submitted the applications to participate by the deadline (1 July 2020),
• the Contracting Authority submits the invitation to negotiate and the preliminary invitation to tender to the selected Tenderers (1 July 2020),
• the Tenderers submit the preliminary tenders (31 July 2020);
3) the negotiations:
• the Contracting Authority conducts negotiations separately with each Tenderer (10 August 2020-18 September 2020),
• the Contracting Authority sends draft invitation to tender to Tenderers for commenting (During the negotiations),
• the Tenderers send their comments on the draft invitation to tender (During the negotiations);
4) the final invitation to tenders and the final tenders:
• the Contracting Authority submits the final invitation to tender to the Tenderers (ASAP when the negotiations have ended),
• the Tenderers submit to the contracting authority the questions concerning the invitation the invitation to tender,
• the Contracting Authority gives answers to the above mentioned questions,
• the Tenderers submit the final tenders (by mid-October 2020);
5) the evaluation of the tenders, the decision on the innovation partnership and the signing of the contract:
• the Contracting Authority evaluates the tenders (by the end of October 2020),
• the Contracting Authority makes the decision on the selection of the tender(s) with whom the Contracting authority will start the innovation partnership (by the end of October 2020),
• the Contracting Authority and the selected innovation partner(s) sign the contract. (target time: 1 November 2020);
6) the innovation partnership begins:
• the first phase: the development and the delivery of the first phase quantum computer,
• the second phase: the development and the delivery of the second phase quantum computer,
• the third phase: the development and the delivery of the third phase quantum computer.
After each phase the Contracting Authority will decide whether it will continue to the next phase with the innovation partner(s) or terminate the innovation partnership. If more than one innovation partners will be selected, after each development phase the Contracting Authority will also decide with whom of the innovation partners the Contracting Authority will continue to the next phase. When making these decisions, the Contracting Authority may, for example, evaluate how well the milestones for the development phase that is about to end, have been achieved.
During the negotiations between the Contracting Authority and the selected Tenderers the development phase, its milestones and above-mentioned evaluation criteria will be negotiated and defined.
If the Contracting Authority decides to terminate the innovation partnership, it may, at its discretion, choose to start a new competitive bidding for the remaining phases or choose to develop and build the next phase quantum computer(s) as its own work.