KYVO3 project will be executed in two phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019. In the second phase in accordance of electricity market development the plant will be supplemented with a 55 MWe CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021. This procurement concerns a steam turbine plant described in more detailed in the Inquiry and its appendices.
Määräaika
Tarjousten vastaanottamisen määräaika oli 2016-12-21.
Hankinta julkaistiin 2016-12-05.
Toimittajat
Seuraavat toimittajat mainitaan hankintapäätöksissä tai muissa hankinta-asiakirjoissa:
hankintailmoitus (2016-12-05) Kohde Hankinnan laajuus
Otsikko: Höyryturbiinit
Lyhyt kuvaus:
KYVO3 project will be executed in two phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with a 55 MWe CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
This procurement concerns a steam turbine plant described in more detailed in the Inquiry and its appendices.
KYVO3 project will be executed in two phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with a 55 MWe CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
This procurement concerns a steam turbine plant described in more detailed in the Inquiry and its appendices.
Ilmoituksen metatiedot
Alkukieli: englanti 🗣️
Asiakirjatyyppi: hankintailmoitus
Sopimuksen luonne: Tavarat
Asetus: Euroopan unioni ja WTO-maat
Yhteinen hankintanimikkeistö (CPV)
Koodi: Höyryturbiinit📦
Lisä-CPV-koodi: Turbiinilaitteistot📦 Suorituspaikka
NUTS-alue: Päijät-Häme
🏙️
Menettely
Menettelyn tyyppi: Neuvottelumenettely
Tarjouksen tyyppi: Tarjous koskee kaikkia eriä
Myöntämisperusteet
Kokonaistaloudellisesti edullisin tarjous
Criteria to reduce the number of the candidates:
See attached Invitation to Participate.
Availability of procurement documents:
Inquiry with the appendices can be request by sending a registration to email address: kyvo3@lahtienergia.fi
The subject field of the registration email shall be marked: KYVO3 / STP / Registration / [name of the candidate].
Registration email shall contain at least name of the candidate company.
The Inquiry will send to all registered candidates.
Submission of the request to participate:
The Request to Participation shall to be emailed to the address: kyvo3@lahtienergia.fi.
Inquiry with the appendices can be request by sending a registration to email address: kyvo3@lahtienergia.fi
The subject field of the registration email shall be marked: KYVO3 / STP / Registration / [name of the candidate].
Registration email shall contain at least name of the candidate company.
The Inquiry will send to all registered candidates.
Submission of the request to participate:
The Request to Participation shall to be emailed to the address: kyvo3@lahtienergia.fi.
Kohde Hankinnan laajuus
Lyhyt kuvaus:
KYVO3 project will be executed in two phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
KYVO3 project will be executed in two phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with a 55 MWe CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
This procurement concerns a steam turbine plant described in more detailed in the Inquiry and its appendices.
Arvioitu kokonaisarvo: 14 000 000 EUR 💰
Lyhyt kuvaus:
This procurement concerns a 55MWe Steam Turbine Plant of KYVO3 project. The Steam Turbine Plant concept is based on district heating with two DH exchangers. The turbine shall have provision for a condensing tail (option). The Steam Turbine Plant will be installed in the existing turbine hall, where it will replace Kymijärvi I turbine. It is planned to be in commercial operation in 2021. Inquiry and its appendices specifies the procurement of the Steam Turbine Plant in more detail.
This procurement concerns a 55MWe Steam Turbine Plant of KYVO3 project. The Steam Turbine Plant concept is based on district heating with two DH exchangers. The turbine shall have provision for a condensing tail (option). The Steam Turbine Plant will be installed in the existing turbine hall, where it will replace Kymijärvi I turbine. It is planned to be in commercial operation in 2021. Inquiry and its appendices specifies the procurement of the Steam Turbine Plant in more detail.
Uudistusten kuvaus:
NTP of the steam turbine plant will be launched based on the development of electricity markets.
Vaihtoehtojen kuvaus:
Option 1 Recommended spare parts
Option 2 Cabling
Option 3 Condensing tail.
Yhteinen hankintanimikkeistö (CPV)
Täydentävä CPV-koodi: KA12
Oikeudelliset, taloudelliset, rahoitukselliset ja tekniset tiedot Osallistumisehdot
Kelpoisuus harjoittaa ammattitoimintaa: See attached Invitation to Participate.
Luettelo ja lyhyt kuvaus säännöistä ja kriteereistä: See attached Invitation to Participate.
Sopimuksen toteuttaminen
Vaadittavat vakuudet ja takuut: Is defined in inquiry/contract.
Tärkeimmät rahoitusehdot ja maksujärjestelyt ja/tai viittaus niitä koskeviin säännöksiin: Is defined in inquiry/contract.
Menettely
Ehdokkaiden vähimmäismäärä: 3
Ehdokkaiden enimmäismäärä: 3
Objektiiviset kriteerit rajoitetun ehdokasjoukon valitsemiseksi: See attached Invitation to Participate.
Tarjousten vastaanottoaika: 13:00
Kielet, joilla tarjoukset tai osallistumishakemukset voidaan jättää: englanti 🗣️
Ilmoitus tehdystä sopimuksesta (2017-09-12) Kohde Hankinnan laajuus
Lyhyt kuvaus:
KYVO3 project will be executed in 2 phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
KYVO3 project will be executed in 2 phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
KYVO3 project will be executed in 2 phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
KYVO3 project will be executed in 2 phases. In the first phase a circulated fluidized bed (CFB) boiler and flue gas condensing plant will be built for heat production. The boiler fuel input is approximately 170 MJ/s and the primary fuels will be forest residue, milled peat and coal. The first phase of the project will be in commercial operation in 2019.
In the second phase in accordance of electricity market development the plant will be supplemented with CHP steam turbine plant. The new turbine is planned to be in commercial operation in 2021.
Procurement consist of the Steam Turbine Plant with auxiliary equipment. The Steam Turbine Plant will be installed in the existing turbine hall, where it will replace Kymijärvi I turbine.
Vaihtoehtojen kuvaus: Cabling and condensing tail.
Suorituspaikka
Pääkohde tai suorituspaikka: Lahti, Kymijärvi power plant.
Sopimuksen tekeminen
Sopimuksen tekemispäivä: 2017-08-10 📅
Nimi: Siemens Osakeyhtiö
Kansallinen rekisterinumero: 0113901-2
Postitoimipaikka: Espoo
Maa: Suomi 🇫🇮 Helsinki-Uusimaa
🏙️
Lähde: OJS 2017/S 176-361066 (2017-09-12)