The procurement process is initially planned to proceed according to the following timetable deadlines (dates in dd.mm.), which the Contracting Authority reserves the right to amend:
6.3.2023 - Submitting questions concerning the procurement procedure, requirements and documentation
10.3.2023 - Answers to presented questions are published in the supplier portal
17.3.2023 - Submitting the application to participate
29.3.2023 - Possible on-site reference visits
31.3.2023 - Selected tender candidates are published
14.4.2023 - Submitting comments regarding the requirements and contract documentation
17.4.2023 - Negotiations start
12.5.2023 - Negotiations end
17.5.2023 - Final invitation to tender is published
31.5.2023 - Submitting questions concerning the final tender
5.6.2023 - Answers to presented questions are published in the supplier portal
19.6.2023 - Submitting the final tender
30.6.2023 - Procurement decision is published
14.7.2023 - Contract signing
The contract can be signed the earliest fourteen (14) days after the procurement decision.
The Contracting Authority reserves the right to change the schedule. The change in the schedule can be affected by e.g. higher than expected needs for clarifications.
In the first phase of the procurement Candidates are invited to submit their Application to Participate. All selected Candidates must meet the minimum requirements.
The Contracting Authority reserves the right to arrange on-site visits to given reference locations in order to inspect the given references. Candidate's contact person must be present during the on-site reference visit and available for assistance and consultation regarding the on-site visit arrangements. Contracting Authority shall not reimburse any costs to the candidates caused by the on-site visits or any other activity regarding the tendering process.
After the potential on-site visits and selection of the tender Candidates, the Contracting Authority will send an invitation to the first negotiation meeting to the selected Tenderers. Negotiation agenda and procedure shall be instructed in the Invitation to Negotiate.
Negotiations are organized in two phases:
Phase 1: Technical, including discussion regarding the technical requirements and demo presentations by the Tenderers
Phase 2: Commercial, including discussion regarding the commercial and contractual requirements
Before the Phase 1, Tenderers are invited to provide feedback, comments and suggestions regarding the client's technical requirements and technical documentation.
Before the Phase 2, Tenderers are invited to provide feedback, comments and suggestions regarding the client's commercial requirements and commercial documentation.
The Contracting Authority may invite the Tenderers to several rounds of meetings.
Tenderer-specific negotiations may be conducted by online call system (Teams or similar) or at the Contracting Authority's headquarters at Helsinki Airport, Finland.
However, the Contracting Authority reserves the right to change the time, place, manner of participation, and form of negotiations.
After completion of the negotiations, the Contracting Authority will draft a final Invitation to Tender and invite all selected Tenderers to submit their tenders,
complying with the terms and conditions determined in the final Invitation to Tender.
Candidates/Tenderers have the opportunity to ask questions at each stage of the Procurement. The Contracting Authority thrives to provide answers as soon as
possible after the deadline.
The procurement documents are available only in English.