Hankinnan kuvaus
Fingrid Oyj, the Finnish national transmission system operator, is initiating a procurement process for 20 kV 63 MVAr dry-type shunt reactors with the intended deliveries during 2023...2025 for existing substations in various locations in Finland.
With this invitation to participate Fingrid is looking for capable and interested suppliers of shunt reactors. In our operating model, the network of service and goods suppliers and good co-operation with suppliers are especially important. We require all our contractual partners who supply us with services or goods to be aware of Fingrid’s significant social duty and to commit to responsibility for the economic, social and environmental effects of their operations.
Delivery consists of four (4) pieces 20 kV 63 MVA shunt reactors and as an option five (5) pieces of 20 kV 63 MVA shunt reactors. Unloading of all reactor sets is included in the scope of delivery.
Preliminary dry-type shunt reactor specification is attached to this prequalification (see attachment PRELIMINARY S22343E1 Dry-type shunt reactor).
Preliminary delivery schedule for deliveries:
3 x 63 MVAr, DDP Simojoki (Q4/2023)
1 x 63 MVAr, DDP Tuovila (Q1/2023)
Preliminary delivery schedule for deliveries (options):
2 x 63 MVAr, DDP Espoo (2024)
3 x 63 MVAr, DDP Hämeenlinna (2025)
See attachment "REA07 Delivery locations".
Delivery locations are preliminary and may be altered during procurement process. Detailed schedules shall be given in the tender inquiry documents.