Process Piping works and materials in Heat Pump Plant Project

Fortum Power and Heat Oy

Fortum Power and Heat Oy is building a 40MW sewage water heat pump plant in Espoo, Finland. Plant will be operated in 2 centrifugal heat pumps a' 20MW output heat power and produced heat will be fed in the District Heating network of Espoo. Total investment budget of the project is 20M EUR.
Piping works for the project will cover the delivery and installation of plant's process piping including pipes, valves, supports and other accessories.
Preliminary schedule of the piping work tendering and projecting will be:
-— tendering in Feb 2014,
— contract sign by end of Feb 2014,
— prefabrication March-April 2014,
— installation works on project site May-September 2014,
— commissioning and hand over of the delivery September-October 2014.
If you are interested to participate to tendering, please leave your application by 10.1.2014 at 16:00 Finnish time to petteri.malinen@fortum.com
In the application please inform the following:
1. Participating company's official name and ID number
2. Main references (>500kEUR value) from recent years
3. Contact information (contact person and e-mail address) where to deliver the offer request.
Offer request will be delivered to accepted applicants. Suppliers which have given competitive offer will be asked for further negotiations.

Määräaika
Tarjousten vastaanottamisen määräaika oli 2014-01-10. Hankinta julkaistiin 2013-11-05.

Kuka?

Mitä?

Hankintojen historia
Päivämäärä Asiakirja
2013-11-05 hankintailmoitus